Private Members Gym
Milestone Key Service:
Project Management & Project Planning
Location:
Jubilee Retail, Canary Wharf, London, E14
Contract Terms:
JCT With CDP
Value:
£1.3m
Introduction
Milestone were appointed to provide specific Project Management and Project Planning functions to enhance the capability of a successful contractor established within the Leisure Industry.
The Construction
Works included the build of a £1.2m Private members gym within an existing retail unit. Total strip out of pre-existing facilities, inclusion of a Mezzanine floor, formation of Acoustic Gym spaces, associated changing facilities and M & E infrastructure. All works in accordance with the strict Canary Wharf Fit-Out guide.
Our Approach
Milestone provided a full Project Management function to supervise the works from Client Pre-start to completion including the responsibility of managing the Project QS, and Site based Project Manager. Providing tailored Client and contractor reviews, reports and inspections for H&S compliance.
Key Deliverables
- Dealing directly with private client.
- Defining scope of works for formation of negotiated cost plan.
- Define a clear procurement plan of subcontractors.
- Define a clear “key Dates” programme for effective commencement of the contract works.
- Coordinate Design team interaction and change management process.
- Enhancing existing process.
- Integrating into a successful established leisure industry contractor to enhance their capability.